Contract ActBreach of Contract 25 May 2026· 5 min read

    P carried extensive milling business. Mill stopped by crankshaft breakage. D engaged to carry shaft to manufacturers. P's servant told D mill was stopped. D delayed delivery causing heavy loss. Action for loss of profits. Decide.

    Audio playback is not supported in this browser.

    The scenario —a mill stopped due to a broken crankshaft, a carrier hired to transport the shaft, the carrier being informed the mill is stopped, a delay by the carrier, and a claim for loss of profits—is a classic illustration of the rules regarding remoteness of damage in contract law.

    Relevant Provision:

    The primary provision governing compensation for loss or damage caused by a breach of contract in India is Section 73 of the Indian Contract Act, 1872,,. It states that:

    "When a contract has been broken, the party who suffers by such breach is entitled to receive, from the other party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it",,.

    The section also clarifies that compensation is not to be given for any remote and indirect loss or damage,.

    Relationship with Hadley v Baxendale:

    Section 73 is understood to incorporate the principles laid down in the English case Hadley v Baxendale (1854) 9 Ex 341,,,,, which is precisely the scenario you've outlined,. This case established two rules for determining recoverable damages:

    1. Losses that arise naturally in the usual course of things from the breach,,.

    2. Losses that arise from special or exceptional circumstances, but only if those circumstances were made known to the party in breach at the time the contract was made, such that the parties could reasonably be supposed to have had them in contemplation as a probable result of the breach,,,.

    Applying the Principle to the present Scenario (and Hadley v Baxendale):

    In the Hadley v Baxendale case itself, the plaintiffs' mill was stopped due to a broken crankshaft, and they engaged the defendant carriers to transport the shaft for repair,. The plaintiffs' servant told the defendants that the mill was stopped and the shaft must be sent immediately. However, the defendants delayed the delivery,. The plaintiffs sued for the loss of profits arising from the mill being stopped for a longer period due to the delay,.

    The original English court in Hadley v Baxendale held the defendants not liable for the loss of profits,. The reasoning was that in the ordinary circumstances of a mill sending a broken shaft for repair, it does not necessarily follow that the mill is stopped; millers might have a spare shaft,. Therefore, the fact that the mill was out of action for want of the shaft was a 'special circumstance' that needed to have been pointed out to the defendants in clear terms, and merely stating the mill was stopped wasn't sufficient to make the loss of profits foreseeable as a natural consequence or one contemplated by both parties in the ordinary course of the carriage contract,.

    The Position under Section 73, Indian Contract Act:

    Section 73 and its illustrations clarify this point. Illustration (i) to Section 73 mirrors the present scenario almost exactly,:

    "(i) A delivers to B, a common carrier, a machine, to be conveyed without delay, to A's mill, informing B that his mill is stopped for want of the machine. B unreasonably delays the delivery of machine, and A in consequence, loses a profitable contract with the Government. A is entitled to receive from B, by way of compensation, the average amount of profits which would have been made by the working of the mill during the time that delivery of it was delayed, but not the loss sustained through the loss of the Government contract (This illustration is a Hadley v Baxendale module)",.

    This illustration is a "Hadley v Baxendale module", demonstrating the application of the second limb of Section 73. Because A informed B that his mill was stopped for want of the machine, this special circumstance was brought to B's knowledge. Consequently, the loss arising directly from this informed special circumstance—the inability to run the mill and earn average profits—is considered to have been known by the parties to be likely to result from the breach,.

    However, any further loss resulting from another special circumstance not communicated, such as the loss of a specific profitable government contract, is considered too remote and not recoverable,,.

    Decision in the above Scenario:

    Based on Section 73 and its Illustration (i), which is specifically relevant here because the carrier was informed that the mill was stopped for want of the machine,:

    • The loss of profits from the working of the mill during the period of delay is a loss arising from a special circumstance that was made known to the carrier at the time of the contract,,.

    • Therefore, the party who suffered the loss (P) would be entitled to receive from the carrier (D), by way of compensation, the average amount of profits which would have been made by the working of the mill during the time that delivery of it was delayed,.

    The compensation recoverable is for loss or damage which the parties knew when they made the contract to be likely to result from the breach,. The communication that the mill was stopped for want of the machine is the key factor under Section 73 and its illustration that makes the loss of general mill profits recoverable, distinguishing it from losses that are truly remote or indirect,.

    In summary, under Indian Law as embodied in Section 73 and illustrated by Illustration (i), the carrier's knowledge of the mill being stopped for want of the shaft makes them liable for the reasonably estimated loss of profits from the mill's operation during the period of delay.

    Share:WhatsAppXLinkedIn

    Get weekly legal insights

    Case-law digests, exam tips & curated study guides — straight to your inbox.

    No spam. Unsubscribe anytime.