Condonation of Delay 06 July 2026· 5 min read

    The Court passed award in land acquisition on 17.07.1970. Application for certified copy was moved on 31.08.1971, copy obtained on 05.01.1972 and appeal was filed on 19.1.1972. It was barred by time. Land Acquisition Officer filed application to have delay excused alleging that government pleader failed to apply for certified copy due to negligence and fraud. Decide.

    Audio playback is not supported in this browser.

    Governing rule

    Section 5 permits an appeal filed after limitation to be admitted only if the appellant satisfies the court that there was sufficient cause for not preferring it in time. The Supreme Court in Ramlal v. Rewa Coalfields Ltd. laid down that the applicant must explain why the appeal was not filed within time and why the delay continued thereafter. In Ajit Singh Thakur Singh v. State of Gujarat, the Court made it clear that the cause must arise within the limitation period itself; later excuses cannot revive a dead remedy.

    Section 12 allows exclusion of the time requisite for obtaining a certified copy, but only the genuine, necessary period can be excluded. A party cannot sleep over its rights and then seek to convert its own lethargy into “time requisite.”

    Applying the dates

    The award was passed on 17.07.1970. The application for certified copy was moved only on 31.08.1971, which itself shows a long and unexplained delay before even taking the first step for appeal. The copy was obtained on 05.01.1972 and the appeal was filed on 19.01.1972.

    Even if the period after the certified-copy application is considered, the real difficulty lies in the silence from 17.07.1970 to 31.08.1971. No explanation is offered for that lapse, and that period cannot be covered by Section 12. The application for condonation therefore fails at the threshold.

    Government pleader’s negligence

    The plea that the Government pleader failed to apply for the certified copy because of negligence and fraud is not enough by itself. The Supreme Court in Special Tehsildar, Land Acquisition, Kerala v. K.V. Ayisumma warned that although some practical latitude may be shown to government files, there is no distinction in principle between the State and a private litigant under Section 5. The Court also observed that the State must still show cogent and reasonable explanation for each day’s delay.

    The commentary further records that where delay in a land acquisition appeal was due to gross negligence of government officers and the affidavit did not disclose proper diligence, the delay was not condoned. In State of U.P. v. Satya Narain and State of U.P. v. Khairati Lal, long delays by the State were refused where no satisfactory cause was shown.

    If fraud by the pleader is specifically proved, the position may be different; but fraud must be pleaded with particulars and supported by material. A bare allegation of fraud, without disclosure of who committed it, when it was discovered, and how it prevented filing, is not enough.

    Illustrative position

    1. If an officer promptly asked for a copy but the court office delayed preparation, the delay may be excused.

    2. If counsel was deceived by forged information and the party acted immediately on discovery, the court may lean toward condonation.

    3. But if the government waited for more than a year before even seeking a certified copy, the real cause is not counsel’s negligence; it is institutional inaction.

    Relevant cases

    In Collector, Land Acquisition, Anantnag v. Katiji, the Supreme Court adopted a liberal approach where the State had shown bona fide delay and no deliberate negligence. In State of Haryana v. Chandra Mani, the Court recognised that governmental decision-making is slower, but still required a genuine explanation. On the other hand, in P.K. Ramachandran v. State of Kerala, the Court refused to condone delay where the explanation was not satisfactory.

    In land acquisition matters specifically, the commentary cites a case where an appeal under Section 54 of the Land Acquisition Act filed with delay was refused because there was absolute lack of good faith and due diligence on the part of the District Attorney. That principle fits this problem squarely.

    Conclusion

    The delay should not be excused. The period between 17.07.1970 and 31.08.1971 remains unexplained, Section 12 cannot rescue that lapse, and the vague plea of negligence and fraud by the Government pleader is not sufficient cause under Section 5. The appeal is therefore time-barred and the condonation application must be rejected.


    Share:WhatsAppXLinkedIn

    Get weekly legal insights

    Case-law digests, exam tips & curated study guides — straight to your inbox.

    No spam. Unsubscribe anytime.